LAKEFRONT PARK PHASE IV

The award winning Kissimmee Lakefront Park redevelopment project has been in the works for over a decade. This final phase runs along Lakeshore Boulevard and connects Kissimmee Lakefront Park to Neptune Road. It will also allow the City to complete necessary sea wall repair.

 

Phase IV will create a larger, linear park space between the roadway and the lake to allow for additional green space, new park benches, and larger pedestrian friendly sidewalks. Lakeshore Drive will also become a brick road and will receive drainage improvements, landscaping, and LED lighting.

The project also calls for the installation of a traffic signal at Neptune Road and Lakeshore Drive, and includes improvements to Brinson Park.

This project is scheduled for completion by Winter of 2019.

Update: October 15, 2018

 

The new brick road surface is being placed along Lakeshore Blvd as progress is being made on Phase IV of the Kissimmee Lakefront Park redevelopment project.

Update: February 7, 2019

Work along Lakeshore Boulevard and Neptune Road is moving along smoothly for the final phase of the Kissimmee Lakefront Park redevelopment project. Underground utilities are complete and the brickwork is 80% done. The project is on track and is projected to be complete by summer 2019.

Update: March 22, 2019

Crews are in the final leg of brick work on Lakeshore Boulevard between Poinsettia Lane and Neptune Road. The outer building shell on the restroom facility at Brinson Park is underway and will be complete around May 2019. Sidewalks on both sides of Lakeshore Boulevard are nearly complete and new street lighting has been installed to match the rest of Kissimmee Lakefront Park. 

Update: May 16, 2019

Brick placement on Lakeshore Blvd has nearly reached Neptune Road, seawall capping and sealing is advancing towards completion, and the outer shell of the new restroom at Brinson Park is complete.

Update: June 5, 2019

As Phase IV of the Kissimmee Lakefront Park redevelopment project moves into its final stages, additional work has begun along Neptune Road. Crews are working on new landscaped medians, sidewalks, utility adjustments and a new traffic signal at Neptune Road and Lakeshore Blvd.

Update: August 6, 2019

100% of brick has been laid along Lakeshore Blvd, landscaping is nearly complete and the sidewalk along Brinson Park has reopened. This project is nearing completion as crews work on sanitary piping, median landscaping and installation of the new traffic signals.